Project Description

We use a variety of technologies to improve multi-modal travel across the city, including upgrading traffic signals. These technologies are known as Intelligent Transportation Systems, or ITS. ITS plays a key role in a safe, efficient, and innovative transportation system that works for all travelers. Much of what we do is not visible to the traveler.

This project will have minor impacts during construction to the southeast corner of Denny Park located at Denny Way and 9th Ave N, on Seattle Parks and Recreation property:

  • Install new Accessible Pedestrian Signals (APS) push buttons on a 4.5-foot pushbutton post.
  • Replace existing signal cabinet at this location with a new signal cabinet equipped with a new service disconnect cabinet.
  • Replace curb ramps at this corner and restore sidewalk pavement.
  • A traffic control plan and pedestrian detours will be in place during construction. Adjacent trees will be protected during construction and any disturbed vegetation will be restored.
  • Minor changes within Denny Park have been determined to be de minimis under Section 4(f) of the U.S. Department of Transportation (USDOT) Act of 1966. Compliance with Section 4(f) is required for projects receiving federal funding.

Project Map

Map showing project area on Denny Way from Western Ave to Minor Ave N.

Funding

This project is funded in part by the 9-year Levy to Move Seattle, approved by voters in 2015, and by funds by the Federal Highway Administration. 

Schedule

Project schedule graphic showing planning phase from early 2016 to late 2018, design phase from late 2018 to late 2021, and construction phase from late 2021 to late 2022.

The project underwent several months of hold during planning and design phases to align scope with funding.

Project Materials

Preconstruction mailer (October 2021)

Construction drop-in session (November 2021)

Other SDOT projects in the area

Transportation

Angela Brady, Interim Director
Address: 700 5th Ave, Suite 3800, Seattle, WA, 98104
Mailing Address: PO Box 34996, Seattle, WA, 98124-4996
Phone: (206) 684-7623
684-Road@seattle.gov

Newsletter Updates

Subscribe

Sign up for the latest updates from Transportation

The Seattle Department of Transportation (SDOT) is on a mission to deliver a transportation system that provides safe and affordable access to places and opportunities for everyone as we work to achieve our vision of Seattle as a thriving, equitable community powered by dependable transportation.