Project Description
We are reestablishing electrical feeds and equipment crossing between Tukwila and South Park. The project will provide a more resilient and reliable power system for nearby customers.
Location

South Park, Seattle
What's Happening Now?
Project Update (July 2026): Project design is approximately 90% complete. We expect to reach 100% completion by the end of fall 2026. We expect construction to begin in early 2027 and continue until October 2028.
Our team will attend a number of community events this summer in South Park. You can meet our project team and learn more at the following events:
- El Mercadito on July 21 and September 22
- SOPASUPA/Duwamish River Festival on August 8
Community Benefits
- Maintain reliable power service throughout the project and minimize impact to South Park residents and businesses.
- Provide better reliability through relocating and undergrounding the double circuit crossing.
Anticipated Impacts
- The construction will cross under the Duwamish Waterway using horizontal directional drilling (HDD).
- Construction will happen entirely upland of the river, launching from industrial parking areas on both sides to protect environmentally sensitive areas, avoid compromising navigation, and maintain public and commercial use of the waterway.

- In addition to running electrical feeds under the river, crews will add new circuits, poles, cables, and vaults.
- As construction wraps up, we will schedule planned power outages so crews can safely connect the new underground system to existing service. We try to notify affected customers at least five days in advance of planned outages.
- Temporary road closures and detours will be in place to mobilize equipment during work hours (exact hours to be determined).
- After construction, all affected areas will be fully restored and repaved according to Seattle Department of Transportation standards. Most of the restoration area is outside of travel lanes and will not impact traffic.
Schedule
Construction Start: Early 2027
Estimated Completion: We expect to complete construction in October 2028.
Daily Work Schedule: To be determined.